Tech Giants Turn to Nuclear Power: Why Atomic Energy Is the New Strategy for Data Centers
This article was created with the help of artificial intelligence.
Key Takeaways
- Microsoft signed a 20-year power purchase agreement worth $16 billion with Constellation Energy in September 2024 to restart the shuttered Three Mile Island nuclear power plant with 835 megawatts of capacity; startup is now targeted for 2027.
- Amazon announced a power purchase agreement on June 11, 2025, covering 1.9 gigawatts from the Susquehanna nuclear power plant in Pennsylvania through 2042 and plans additional investments exceeding $20 billion in AWS data center infrastructure in Pennsylvania.
- Global electricity demand for data centers will rise from 460 terawatt-hours in 2024 to over 1,000 terawatt-hours in 2030 and 1,300 terawatt-hours in 2035, according to Deloitte analysis.
- Google signed the first U.S. fleet agreement for modular small reactors with Kairos Power covering up to 500 megawatts of capacity with delivery scheduled to begin in 2030, while Meta launched a request for proposals for 1 to 4 gigawatts of new nuclear capacity.
- The global pipeline for Small Modular Reactors reached 47 gigawatts by the end of the first quarter of 2025, with more than half of this capacity located in the U.S.
The technology industry is undergoing an energy policy reversal: nuclear power, long viewed as a technology in decline, is becoming strategic infrastructure for artificial intelligence. By December 2025, major U.S. tech companies had signed contracts for more than 10 gigawatts of new nuclear capacity within a single year. Microsoft, Amazon, Google, and Meta are positioning themselves as the driving force behind the nuclear renaissance.
The reason for this development lies in the physical limitations of renewable energy: a single new AI data center consumes as much electricity as the city of Chicago. Nuclear power provides carbon-free baseload energy around the clock—a combination that solar and wind power cannot offer.
Why Nuclear Power Becomes Essential for AI Data Centers
Data center electricity demand is growing exponentially. According to a Deloitte analysis from April 2025, global power generation for data centers will rise from 460 terawatt-hours in 2024 to over 1,000 terawatt-hours in 2030 and reach 1,300 terawatt-hours in 2035. Nuclear energy could cover up to 10 percent of data center electricity demand by 2035.
This massive increase reflects the demands of modern AI systems. Large language models and image generators require continuous computing power, which in turn requires stable power supply. Renewable energy can cover peak loads but fails to deliver 24/7 availability without costly storage solutions.
Add to this the sustainability commitments of hyperscalers: Microsoft, Amazon, Google, and Meta have committed to carbon neutrality. This rules out coal or natural gas power plants, while available grid capacity for renewable energy is already largely exhausted.
Microsoft's $16 Billion Bet on Three Mile Island
Microsoft signed a 20-year power purchase agreement worth $16 billion with Constellation Energy in September 2024. The deal involves restarting the reactor at Three Mile Island nuclear power plant in Pennsylvania, which was shut down in 2019. The facility with a capacity of 835 megawatts will return to operation under the new name Crane Clean Energy Center. Originally scheduled for 2028, after grid operator PJM approved expedited grid connection, Constellation is now targeting 2027 for startup.
Microsoft secures 100 percent of the power plant's output—a scale far exceeding the company's previous solar and wind power contracts. Constellation had shut down the reactor in 2019 for economic reasons, as operating costs could not be covered at declining electricity prices. Microsoft's long-term purchasing commitment now provides the financial security for reactivation.
The reactor block designated for restart was not involved in the partial meltdown of 1979. Constellation filed for a facility renaming in February 2025, submitted an updated decommissioning report in March, and filed for removal of operating restrictions between April and June 2025. On June 25, 2025, Pennsylvania Governor Josh Shapiro appeared with representatives from Constellation and Microsoft to welcome returning workers.
A Microsoft energy strategy manager explained in September 2024: "There is this really untapped resource of nuclear energy that exists or has recently left the grid because economics displaced it, as more renewables come online."
Amazon's Diversified Nuclear Strategy
Amazon takes a different approach than Microsoft: instead of relying on a single partner, the company diversifies across multiple nuclear energy projects. On June 11, 2025, Amazon announced a power purchase agreement with Talen Energy covering 1.9 gigawatts from the Susquehanna nuclear power plant in Pennsylvania through 2042. The contract supports Amazon's plan to invest over $20 billion in Amazon Web Services infrastructure in Pennsylvania to power new and existing data centers in the region.
In parallel, Amazon is developing technology for Small Modular Reactors (SMR) near the Dominion Energy North Anna nuclear facility in Virginia. The company made these SMR investments public in October 2024. SMRs are smaller reactor units with approximately one-third the output of conventional plants (250 to 300 megawatts versus 800 megawatts for traditional reactors).
Google and Meta: Innovation versus Flexibility
Google concluded the first U.S. fleet agreement for modular small reactors with Kairos Power. The agreement covers up to 500 megawatts of SMR capacity with delivery scheduled to begin in 2030. Google positions itself as a champion of experimental nuclear technology and deliberately assumes higher technological risk than Microsoft or Amazon.
Meta chose a more flexible approach: the company launched a request for proposals for 1 to 4 gigawatts of new nuclear capacity. With this RFP, Meta keeps open the option to negotiate with multiple suppliers and combine different technologies.
Small Modular Reactors: The Next Generation
SMRs are considered a key technology for powering data centers. The global project pipeline for modular small reactors reached 47 gigawatts by the end of the first quarter of 2025, with more than half of this capacity located in the U.S. according to Wood Mackenzie forecasts.
The modular design offers several advantages: shorter construction times, lower investment costs per unit, and the ability to expand capacity incrementally. However, a challenge also emerges: AI data centers can require up to 5 gigawatts of power, necessitating multiple SMR units or hybrid approaches with conventional reactors.
Political Tailwind for the Nuclear Industry
The regulatory landscape has shifted significantly in favor of nuclear energy. President Donald Trump signed executive orders promoting the U.S. nuclear industry, including a directive to expand installed nuclear capacity from the current 100 gigawatts to 400 gigawatts by 2050 and promote advanced technologies. The administration supported the restart of a reactor in Michigan that had received a $1.5 billion rescue loan under the Biden administration.
According to a Barclays analysis from October 2025, governments worldwide are identifying nuclear energy as a clean, stable, and energy-dense solution. This process is being accelerated by the demand of major cloud service providers.
Four Different Strategies, One Goal
The four tech giants pursue different approaches reflecting their respective risk profiles:
- Microsoft optimizes for speed through dependence on a single supplier (Constellation Energy) and promises Azure customers faster availability of carbon-free energy.
- Amazon prioritizes reliability through diversified partnerships and offers AWS infrastructure with higher fault tolerance.
- Google focuses on technological progress by promoting experimental SMR development, with Google Cloud customers bearing the innovation risk.
- Meta relies on flexible procurement through competitive bidding and maintains optionality across multiple suppliers.
Timeline of Tech Nuclear Policy
The shift to nuclear power occurred in several steps: in May 2023, Microsoft signed its first publicly known nuclear contract with fusion company Helion Energy. In October 2024, Amazon disclosed its SMR investments. Also in October 2024, Google agreed to the Kairos Power contract, and in December 2024, Meta launched its request for proposals. This was followed by Amazon's Susquehanna agreement on June 11, 2025. By December 2025, the industry had documented contracts for more than 10 gigawatts of new U.S. nuclear capacity within a single year.
Outlook: From Niche to Core Technology
Tech companies' decisions are fundamentally changing the perception of nuclear energy. What for years was regarded as an unprofitable declining technology is becoming strategic infrastructure for the digital economy. The long-term power purchase agreements of hyperscalers create the financial foundation for reactor restarts and new technologies like SMR.
At the same time, challenges emerge: the planned startups lie years in the future, while electricity demand is already growing today. Microsoft's Three Mile Island is scheduled to go online in 2027, Google's SMR fleet from 2030 onward. Until then, tech companies remain dependent on existing grids and conventional power sources.
The four different strategies also reflect uncertainty about optimal technology: should companies rely on proven large-scale power plants, experimental SMRs, or hybrid approaches? The coming years will show which approach proves superior economically and technically.
Sources
- Nuclear power for AI: inside the data center energy deals
- Amazon, Google, Meta and Microsoft go nuclear
- Why Microsoft And Amazon Are Turning To Nuclear Power For AI
- Why tech giants such as Microsoft, Amazon, Google and Meta are betting big on nuclear power
- Big Tech Embraces Nuclear Power to Fuel AI and Data Centers - IEEE Spectrum
- Crane Clean Energy Centre on track for ahead-of-schedule restart